The claim for compensation under Section 642 of the German Civil Code (BGB) requires that the contractor offers to perform the work in accordance with Section 295 BGB and is capable of doing so. If no offer to perform has been made, or if the contractor is engaged in other work on the same construction site, the client cannot be deemed to be in default of acceptance. Section 6(6) of the VOB/B does not apply in the event of hindrances caused by subcontractors if the client has not assumed any specific liability. Additional remuneration under Section 2(5) of the VOB/B requires a genuine instruction that alters the construction schedule; mere notification of hindering circumstances is not sufficient.
Facts of the case
The claimant had been commissioned by the defendant to carry out landscaping works at a comprehensive school in accordance with the VOB/B. The contract value amounted to approximately EUR 1.15 million. Following a previous halt to construction, the claimant commenced work in September 2018, which came to a standstill as early as the beginning of December 2018. Between December 2018 and June 2019, the claimant notified the defendant in writing of hindrances on a total of five occasions. Specifically:
The claimant justified its first notice of hindrance, dated 6 December 2018, on the grounds of a lack of access to the site. A goods lift and scaffolding were situated within its work area, and subcontractors were occupying the space. The claimant was therefore unable to carry out the work (laying gravel for the sub-base, installing bicycle racks and paving the areas, and carrying out drainage work).
On 21 December 2018, the restrictions persisted, which is why the claimant again reported an obstruction. All work that could have been completed up to that point had already been finished. The parties were also unable to arrange for work to continue in stages elsewhere, as numerous other firms were still engaged in, amongst other things, interior fit-out and façade construction. The claimant therefore announced that it would suspend work over Christmas and was expected to resume in early February.
On 14 February 2019, the claimant again reported a hindrance to the works. From 11 March 2019, it was able to resume work in certain areas. On 11 April 2019, all parties involved in the project agreed at a site meeting that, due to a lack of preliminary work (including sandblasting, façade and plinth work), it would not be economically viable for the claimant to carry out work on the relevant areas (main and side entrances, refuse collection point, inner courtyard) until the end of the 22nd calendar week (up to 2 June 2019). On 17 May 2019 and 3 June 2019, the claimant again reported that work was being impeded and, on each occasion, expressly offered to carry out its work, including the provision of staff and equipment. From 11 June 2019, the claimant carried out additional work.
The claimant brought a claim before the Regional Court of Cologne for payment of EUR 508,758.07. It contends that it is entitled to claims under Section 642 of the German Civil Code (BGB), Section 6(6) of the VOB/B and Section 2(5) of the VOB/B, as it was prevented from performing its work during five separate periods between January and June 2019. The Regional Court issued a judgment on the merits, according to which the claimant is entitled, in principle, to payment of reasonable compensation for all five periods claimed.
Decision
The defendant’s appeal against this judgment is partially successful. The court rejects the claimant’s claims for compensation for delays in construction for three of the five periods claimed.
Reasonable compensation under Section 642 of the German Civil Code (BGB) is ruled out for the three periods because there was no default in acceptance in the first place:
Period 1 (2 January to 13 February 2019): The court ruled that the conditions for default on acceptance were not met, as there was no verbal offer of performance by the claimant as required under Section 295 of the German Civil Code (BGB). Nor could the written notice of hindrance dated 21 December 2018 be interpreted as an offer of performance. Admittedly, the statements contained therein – indicating, amongst other things, that work in the side entrance area was still not possible and, following consultation with the building services department, would only be available at the end of the third week of January – suggested that the claimant intended to perform the services owed by it and thus to offer them. However, the sentence also contained in this letter—‘We have therefore come to the conclusion that we will suspend the work over Christmas and are expected to resume it at the beginning of February’—contradicts such an implied offer. In doing so, the claimant had indicated that it did not intend to carry out any further work until at least the beginning of February, even though, according to its previous statements, this would have been possible again from the fourth week of January onwards. Against this background, it is not possible to interpret the content of the notice of impediment dated 21 December 2018 as an offer to perform.
Period 2 (15 April to 28 June 2019): Nor was the defendant in default of acceptance during this period. Admittedly, a notice of impediment would have been dispensable, as the defendant’s impeding circumstances were evidently known from construction meetings (Section 6(1), second sentence, VOB/B). However, this does not alter the fact that, for this period, an offer of performance from the claimant – which is not present here – would have been required.
Period 3 (11 June to 28 June 2019): Again, no default in acceptance. This is because, during this period, the defendant was unable, in accordance with Section 297 of the German Civil Code (BGB), to perform the service offered to the claimant, as it was already engaged in other (additional) works.
The court also rejects a claim for damages under Section 6(6) of the VOB/B. Such a claim would require that the defendant be responsible for the circumstances hindering performance. Liability for vicarious agents under Section 278 of the BGB might also be considered. However, this would only apply insofar as they were actually required to fulfil a duty in relation to the contractor whose work was impeded. In this respect, according to the case law of the Federal Court of Justice (BGH), subcontractors are excluded if the client – as is usually the case – has not assumed any specific liability. It has neither been argued nor is it otherwise apparent that the defendant had assumed such a specific obligation to indemnify them. Consequently, there is no breach of duty for which the defendant is responsible, because whilst the subcontractors caused the hindrance, they are not the defendant’s vicarious agents in the relationship with the defendant.
A claim for additional remuneration under Section 2(5) of the VOB/B is also ruled out. Such a claim would require an instruction from the defendant that altered the basis of the price for a service provided for in the contract. Admittedly, in principle, an instruction affecting the construction schedule could also give rise to claims under Section 2(5) of the VOB/B. However, not every ‘hindrance’ caused by a third party, which the client ‘notifies’ to the contractor, constitutes an instruction with the effect of triggering the legal consequences under Section 2(5) of the VOB/B. Otherwise, the requirement of fault under Section 6(6) of the VOB/B would be completely circumvented. Merely by notifying the contractor of hindering circumstances, the client, correctly interpreted, neither issued an instruction nor (impliedly) offered to amend the contractual arrangements regarding the construction period.
The court, however, upheld claims for two periods:
Periods 4 and 5 (14 February to 8 March 2019 and 29 April to 10 June 2019): For these periods, the court found that all the conditions of Section 642 of the German Civil Code (BGB) were met. With the notices of hindrance dated 14 February, 29 April, 17 May and 3 June 2019, the claimant had duly offered to perform its obligations – including the provision of staff and equipment – and was prepared to do so. The defendant’s objection that work had not been possible in winter due to weather conditions was not persuasive – the defendant itself had assumed in its order that work would commence in January 2018.
Practical advice
Contractors should ensure that they always clearly state their willingness and ability to perform the work in their notices of hindrance. Statements indicating an intention to suspend work – even if prompted by the hindrance – may be interpreted as a withdrawal of the offer to perform and could jeopardise the claim for compensation.
Anyone carrying out additional work on the same construction site risks losing their claim for compensation for that period, as their capacity to perform the main contract may cease to exist in accordance with Section 297 of the German Civil Code (BGB). It is advisable to document capacity planning carefully.
(Higher Regional Court of Cologne, judgement of 24 July 2026, ref.: 7 U 97/24)